Contact Information Management System

Project Plan


Initial Discussions7/1 - 8/31
Prepare Project Proposal9/1 - 9/3
Project Proposal9/6
Approval of Project Proposal9/20
System Analysis9/20 - 9/27
System Design9/28 - 10/11
Software Selection10/12 - 10/28
Detailed Project Plan10/28
Approval of Project Plan11/1
Software Acquisition11/2 - 11/4
Implementation11/5 - 11/26
User Acceptance Testing11/29 - 12/3
Data Conversion12/6 - 1/3
Prepare User Training Materials12/20 - 12/31
User Training1/4 - 1/31
System Evaluation2/1 - 3/15